14th May 2025 9:11:48 AM
2 mins readThe technical glitch that occurred on the FPSO Kwame Nkrumah (KNK) over the weekend has been resolved, enabling, lead operator of the Jubilee Field, Tullow Ghana, to begin operations at the Jubilee Field.With the gas supply restored, power generation is set to improve while reliance on other energy sources is expected to decrease.
0
Tullow Ghana in a statement on Tuesday, May 13, indicated that the issue has been rectified allowing the safe and efficient resumption of operations.
1
“As of Monday, 12 May, we resumed exporting approximately 100 million standard cubic feet per day (mmscfd) of gas to the Atuabo gas processing plant, which will contribute to supporting Ghana’s domestic energy needs,” the statement said.An official statement released by the Ministry of Energy and Green Transition on Saturday, May 10, indicated that the issue has since halted the regular flow of gas from the FPSO unit.
2
The FPSO Kwame Nkrumah is a key installation in Ghana’s offshore oil and gas production infrastructure, and the affected compressor plays a critical role in gas processing and delivery.The Ministry in a release on Sunday, May 11, noted
3
As a result, the technical failure had a direct impact on the consistency of gas supply to downstream users.
4
“Initial assessments suggest the need for significant repairs. The team is currently working diligently to implement necessary repairs to restore the supply of gas as soon as possible,” the statement said.
5
The Ministry added that although the disruption is temporary, the damage to the compressor requires complex interventions, and restoring full operations will depend on the extent of repair work needed.
6
Authorities are currently evaluating all possible measures to expedite the process without compromising safety or equipment standards.
7
While the Ministry did not immediately specify how long the disruption would last, it acknowledged the potential implications for power generation and industrial operations that depend on consistent gas flow.
8
As part of its response strategy, the Ministry noted that it is coordinating with relevant stakeholders in the energy sector, including power generation companies and regulators, to manage the situation and mitigate any ripple effects on electricity supply and industry operations.
9
It added that further updates will be communicated to the public as work progresses on the FPSO vessel.
10
The Ministry has, therefore, assured citizens and industry partners of its commitment to resolving the issue promptly and maintaining transparency throughout the repair period.