Akosombo Dam Spillage: Probe ends, 15 major disaster lapses revealed

10th May 2025 11:03:53 AM

4 mins read
Twitter |   Facebook |   WhatsApp
akosombo-dam-spillage-probe-ends-15-major-disaster-lapses-revealed

The committee tasked to initiate a probe into the 2023 Akosombo Dam spillage has concluded its findings.Dam spillage that occurred in September 2023 displaced many, caused serious destruction of properties, as well as put disrupted the livelihoods of individuals residing in the Lower Volta Basin.About 38,624 victims being displaced, with the worst-affected areas identified as North Tongu, Central Tongu, South Tongu, Ada and Kpong jurisdictions.The floods swept away, approximately 1,247 homes, 94 schools, and 17 health facilities, while agricultural loses alone are estimated at  $78 million.In response the then Akufo-Addo-led administration provided relief items and supported rescue efforts.Two years on, President John Dramani Mahama appointed the five-member investigative committee to look into factors that may have caused the disaster.The committee underwent two months of intensive investigation producing critical findings and actionable solutions.The committee in a 110-page report, submitted to President Mahama via the Minister of Energy and Green Transition, John Abdulai Jinapor, on May 7, called for urgent policy reforms to prevent similar crises in the future.1. Factors that determine water spillage from the dam include reservoir elevation, rainfall and energy output from the power plant.

0

2. The Akosombo Dam recorded a maximum water inflow of 477,984 cubic feet per second (cfs) on September 18, 2023, at the Akosombo hydrometric station.

1

3. The 2023 Spill occurred between September 15 and October 30, 2023. The total volume of water discharged from the spillway was approximately 8 Million Acre Feet (MAF) for 46 days.

2

4. Historical spillage exercises have shown that in 1968, the volume was 5 times the volume spilled in 2023, indicating that there could be larger volumes of spill in the future due to climate change uncertainties.

3

5. Examination of Events Leading to Spillage: The spillage was primarily caused by releasing approximately 8 MAF volumes of water from the Akosombo Dam to prevent the dam’s destruction (overtopping) due to high reservoir water levels. Other contributing factors included unprecedented rainfall due to climate change and human activities exacerbating flood risks. Breaching the dam could have resulted in a catastrophic chain of events in the country.

4

6. VRA’s Emergency Preparedness Plan (EPP): The EPP specifies the roles and responsibilities of all stakeholders, including VRA, NADMO, District Assemblies, Security Agencies, etc., when an emergency occurs. The EPP was used to manage the disaster caused by the spillage and was the most technical document to be understood by various non-technical stakeholders. While VRA had socialised the document with all stakeholders and conducted a simulation exercise for some selected communities before the spill, high turnout and divisions amongst some District Chief Executives (DCEs)/Metropolitan Chief Executives (MCEs) and Members of Parliament (MPs) could have derailed clear communication lines for implementing the plan and distribution of relief items.

5

7. Assessment of Actions Taken: The response involved various government agencies, including the Volta River Authority (VRA) and the National Disaster

6

Management Organisation (NADMO). While there were efforts to provide immediate assistance, gaps in communication, resource allocation, and community engagement were identified.

7

8. Challenges Encountered: The Committee noted operational challenges, such as a lack of local disaster preparedness plans and inadequate evacuation resources, that hampered the emergency response process. Communication breakdowns and skepticism among community members regarding the information provided by authorities further complicated response efforts.

8

9. Community Challenges: The Committee also noted that land tenure attachment by the people, economic reliance on location, fear of unpredictability, insufficient financial resources and support from Authorities, restricted housing options, historical precedence of spillage and cultural resistance were factors that made most affected people unwilling to relocate during the spill event.

9

10. Temporal accommodation: The Committee noted with concern that some affected persons were still housed in tents, at the mercy of the weather, refusing to relocate to temporary accommodation built by VRA. They cited a lack of privacy as families were required to share rooms.

10

11. Resettlement: Some Government-initiated resettlement projects are far from the people’s previous abode. The people lament that their opinions were not sought in selecting the sites for the resettlement, and therefore, have refused to relocate and are requesting that the resettlement project be halted as the objective is not served.12. Compensation: Since the spillage occurred, in communities upstream and downstream, the affected people in these communities have not been adequately compensated for the devastating impact the floods had on their properties and source of livelihoods. Some also expressed displeasure that though they suffered and continue to suffer the direct effects of the dam, they were not compensated when the Akosombo dam was built.

11

13. Evaluation of Strategies: The strategies employed to manage the situation revealed short-term and long-term effectiveness. However, improvements were necessary in community education and disaster management protocols.

12

14. Proposals for Additional Measures: To mitigate future risks, recommendations were made for enhancing emergency response protocols, improving community engagement, and implementing stricter land use regulations.

13

15. Communities Upstream: Several communities located upstream of the dam experienced significant flooding, resulting in the submersion of homes and

14

farmland. The rising water levels inundated large portions of agricultural land, leading to the loss of crops and threatening the livelihoods of affected farmers.

15

More News

Ghanaian women kidnapped in Nigeria return to Ghana - Police

2 mins read

Wendy Shay gifts cash to god-daughter's father at his furniture shop

1 min read

Kinaata honoured by Otumfuo for inspiring, educating youth through music

1 min read

Famela GH receives GHS2000 prize for singing Criss Waddle's song

1 min read

Mahama never received vehicles from NSB, he won’t stoop low to that - Tanko-Computer

1 min read

Akosombo Dam Spillage: Probe ends, 15 major disaster lapses revealed

4 mins read

Adwoa Safo pens loving note to son Ohene on his birthday

1 min read

Kinaata confident of grabbing 3 awards to complete his trophy cabinet

2 mins read

A/R: Accident on Krofrom leaves several injured

1 min read

Newspaper

Recent Stories

Ghanaian women kidnapped in Nigeria return to Ghana - Police

Ghanaian women kidnapped in Nigeria return to Ghana - Police

2 mins read

Wendy Shay gifts cash to god-daughter's father at his furniture shop

Wendy Shay gifts cash to god-daughter's father at his furniture shop

1 min read

Kinaata honoured by Otumfuo for inspiring, educating youth through music

Kinaata honoured by Otumfuo for inspiring, educating youth through music

1 min read

Famela GH receives GHS2000 prize for singing Criss Waddle's song

Famela GH receives GHS2000 prize for singing Criss Waddle's song

1 min read

Mahama never received vehicles from NSB, he won’t stoop low to that - Tanko-Computer

Mahama never received vehicles from NSB, he won’t stoop low to that - Tanko-Computer

1 min read

Akosombo Dam Spillage: Probe ends, 15 major disaster lapses revealed

Akosombo Dam Spillage: Probe ends, 15 major disaster lapses revealed

4 mins read

Adwoa Safo pens loving note to son Ohene on his birthday

Adwoa Safo pens loving note to son Ohene on his birthday

1 min read

Kinaata confident of grabbing 3 awards to complete his trophy cabinet

Kinaata confident of grabbing 3 awards to complete his trophy cabinet

2 mins read

A/R: Accident on Krofrom leaves several injured

A/R: Accident on Krofrom leaves several injured

1 min read