The West African Gas Pipeline Company Limited (WAPCo) has reported that 70% of its repair operations are complete, bringing the company closer to reinstating gas flow to Tema.
The maintenance work, which involves a deep-sea pipeline cleansing and assessment process called pigging, began on February 3, 2025, and is projected to conclude by March 2, 2025.
Addressing journalists at WAPCo’s facility in the Tema Industrial Zone, Engineer Benoni Owusu Ayeh, the Operations and Maintenance Superintendent for Western Operations, expressed confidence in the project's progress.
“Looking at the travel distance and what we communicated, we believe that we should be able to complete this exercise before 2nd March. We’re within schedule and we believe that until something happens – but based on what we’ve seen we’re making progress.
“We hope to resume supply to Tema, and also Lomé. We’ll still have to carry out some activities to the Cotonou lateral. Because from the Tema job, the vessel will move to Cotonou. Cotonou we’re doing an inspection, we run several pigs, about six of them. So Cotonou will not be able to resume, 2nd March. We are either looking at either 5th or 7th March. But for reverse flow and Tema, we should be ready before 2nd March,” he noted.
He added that while gas supply to Tema and Lomé should resume as expected, further work is required for the Cotonou section.
These upgrades are essential for enhancing the pipeline’s performance and ensuring a steady energy supply for Ghana.